FG gives date for reopening of Third Mainland Bridge

Must read

The Federal Controller of Works Lagos, Mr Olukayode Popoola, says the total shutdown of the Third Mainland Bridge would be lifted on Sunday, December 27.

Popoola told the News Agency of Nigeria on Sunday in Lagos that the total shutdown had to be lifted because the contractor was able to fast-track the delicate task they needed to execute.

He said that the initially scheduled 72 hours timeframe was achieved within 48 hours, hence the reopening to traffic 24 hours ahead of schedule.

“We have completed the casting of the three number expansion joints on Third Mainland bridge.

“Therefore, the bridge shall be opened at 12:00 midnight Sunday 27th December, and no longer Monday 28th December.

READ ALSO: Enemies of the country will lose las las – Femi Adesina

“That is 48 hours and no more 72 hours,” Popoola said.

The controller had on Tuesday, December 22 announced a 72 hours total shutdown of the bridge with effect from midnight on Saturday to midnight Tuesday.

The shutdown was to stop vibrations caused by the movement of vehicles for contractors to cast concrete on additional three expansion joints in the ongoing rehabilitation of the bridge.

NAN reports that the Third Mainland Bridge which was going through a series of repairs had to be partially shut on July 24 for another round of rehabilitation works.

The repair that was expected to last six months was extended by one month due to the recent #EndSARS protests in Lagos, thereby extending the completion date from January 2021 to February.

Copyright DAYBREAK NIGERIA.

All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express written permission from DAYBREAK NIGERIA.

More articles

1506 COMMENTS

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest article