FG Lists Steps Taken To Restore ‘Normal Supply Of Electricity’ Nationwide

The Federal Government on Saturday said it has taken several steps “towards the restoration of normal supply of electricity nationwide.”

The national grid suffered shutdowns at least twice in the past week leading to blackouts across the country amid rising prices of fuel products.

In a statement signed by Minister of Power, Abubakar Aliyu, the government said it had made some progress to address the recent challenges.

“The Nigerian public may please recall that the national grid lost 1,110 MW generation capacity as a consequence of simultaneous disruptions in gas supply to the Okpai, Calabar and the Afam VI power plants,” the statement said.

“The available generation capacity was exacerbated by the ongoing water management regime at the Kainji, Jebba and Shiroro power plants.”

According to the Minister, the steps taken to address the situation include the following:

a. The gas pipeline affected by acts of vandalism has been restored and the Okpai power plant has resumed power generation and currently contributing an average of 300MW.

b. The Nigerian Bulk Electricity Trading Plc has been directed to enter into fast-track negotiation with NAOC on an interim energy sales agreement with a view to bringing the new Okpai II power plant on the grid, thereby contributing additional 400MW of generation capacity.

c. The “pigging” of the gas pipeline supplying gas to the Odukpani power plant is scheduled for completion on March 21st, 2022, thus ramping up generation by about 400MW.

d. In order to optimise the capacity utilisation of the power plants owned by the Niger Delta Power Holding Company Ltd (NDPHC), the Nigerian Electricity Regulatory Commission has approved a special gas pricing for emergency contracting of gas from the Nigerian Gas Marketing Company Ltd. We expect an ongrid improvement of about 800MW generation capacity from the NDPHC plants.

e. In the medium-term, we have agreed with NGPIC (a subsidiary of NNPC) on the framework for the overhaul of the Okoloma gas processing plant thereby restoring the full capacity of the 650MW Afam VI combined cycle power plant.

f. While the recent spate of system collapse is regrettable, it was a direct consequence of a snap on 330KV transmission line. The mitigation measures for avoiding such incidence of blackouts are being impemented through several interventions including the Presidential Power Initiative.

Hot this week

Arewa Youth Group Calls for Defence Minister’s Removal Over Security Concerns

By Achadu Gabriel, KadunaA northern youth group has...

NMWF Supports Healthcare , Upgrades Sections of Zuba General Hospital

By Joyce Remi- BabayejuThe Nigerian Ministers' Wives Forum (NMWF)...

Kaduna Government Warns Against Illegal Land Sales at NNPC Quarters in Sabon Tasha

By Achadu Gabriel, KadunaThe Kaduna State Government has...

Dogara Celebrates Baba Jang at 82, Hails Him as a Visionary Statesman

Former Speaker of the House of Representatives and Chairman,...

FG Gets Long-Acting Injectable Lenacapavir for Strengthen HIV Prevention in Nigeria

By Joyce Remi-BabayejuThe Federal Government has received the Long-Acting...

Nasarawa North CAN Backs Gov. Sule, Urges Senate Bid in 2027

By Abel Zwanke, LafiaThe Christian Association of Nigeria (CAN)...

Shiite Protest Disrupts Traffic, Business Activities in Kaduna

By Achadu Gabriel, KadunaHundreds of members of the...

TCN Begins Construction of 330kV Transmission Line at Ihovbor to Boost Power Supply

By Jabiru HassanThe Transmission Company of Nigeria (TCN)...

Riyom Council Congratulates Gov. Mutfwang at 61, Commends Peace Efforts

By Israel Adamu, JosThe Executive Chairman of Riyom Local...

Delta Approves Over ₦400bn for Roads, Security, Infrastructure Projects

By Anne AzukaThe Delta State Government has approved infrastructure...

I’ ll contest for Nasarawa Governor in 2027, says Ombugadu

The two People's Democratic Party ( PDP) Governorship candidate...

Related Articles

Popular Categories

spot_imgspot_img