FG Lists Steps Taken To Restore ‘Normal Supply Of Electricity’ Nationwide

The Federal Government on Saturday said it has taken several steps “towards the restoration of normal supply of electricity nationwide.”

The national grid suffered shutdowns at least twice in the past week leading to blackouts across the country amid rising prices of fuel products.

In a statement signed by Minister of Power, Abubakar Aliyu, the government said it had made some progress to address the recent challenges.

“The Nigerian public may please recall that the national grid lost 1,110 MW generation capacity as a consequence of simultaneous disruptions in gas supply to the Okpai, Calabar and the Afam VI power plants,” the statement said.

“The available generation capacity was exacerbated by the ongoing water management regime at the Kainji, Jebba and Shiroro power plants.”

According to the Minister, the steps taken to address the situation include the following:

a. The gas pipeline affected by acts of vandalism has been restored and the Okpai power plant has resumed power generation and currently contributing an average of 300MW.

b. The Nigerian Bulk Electricity Trading Plc has been directed to enter into fast-track negotiation with NAOC on an interim energy sales agreement with a view to bringing the new Okpai II power plant on the grid, thereby contributing additional 400MW of generation capacity.

c. The “pigging” of the gas pipeline supplying gas to the Odukpani power plant is scheduled for completion on March 21st, 2022, thus ramping up generation by about 400MW.

d. In order to optimise the capacity utilisation of the power plants owned by the Niger Delta Power Holding Company Ltd (NDPHC), the Nigerian Electricity Regulatory Commission has approved a special gas pricing for emergency contracting of gas from the Nigerian Gas Marketing Company Ltd. We expect an ongrid improvement of about 800MW generation capacity from the NDPHC plants.

e. In the medium-term, we have agreed with NGPIC (a subsidiary of NNPC) on the framework for the overhaul of the Okoloma gas processing plant thereby restoring the full capacity of the 650MW Afam VI combined cycle power plant.

f. While the recent spate of system collapse is regrettable, it was a direct consequence of a snap on 330KV transmission line. The mitigation measures for avoiding such incidence of blackouts are being impemented through several interventions including the Presidential Power Initiative.

Hot this week

Plateau PDP group pledge to support factional National Chairman Abdulraham Mohammed

By Israel Adamu,JosPlateau PDP Progressive Vanguard on Sunday...

NEMA Dialogues Assembly Committees for Disaster Management Legislative Support

By Joyce Remi-BabayejuThe National Emergency Management Agency (NEMA)...

Apostle Kure Claims Churches Denied in Northern Nigeria, Hails Trump’s “Country of Concern” Designation

By Achadu Gabriel, KadunaUnited States President Donald Trump’s designation...

CSO Urges Tinubu, Governors to Approve Loan to Save Nigerian Pilgrims from Missing 2026 Hajj

By Jabiru HassanThe Independent Hajj Reporters (IHR), a faith-based...

NCDMB to Honour 2025 National Essay Competition Winners in Yenagoa

By Amgbare Prince, YenagoaThe Nigerian Content Development and Monitoring...

FG Abandons Indigenous Language Policy, Adopts English as Sole Medium of Instruction

The Federal Government has officially abolished the policy mandating...

Army Reaffirms Commitment to Curb Banditry, Assures Citizens of Safety in Kogi

By Noah Ocheni, LokojaThe Commander of the 12 Brigade,...

Insecurity: Bandits Abduct Six Defence Ministry Directors on Kaba–Lokoja Highway

By Noah Ocheni, LokojaSix senior directors of the Federal...

FG Inaugurates Inter-Ministerial Committee to Enforce Ban on Single-Use Plastics Nationwide

By Francis WilfredThe Federal Government has inaugurated an Inter-Ministerial...

Related Articles

Popular Categories

spot_imgspot_img