FG Rejigs Project Delivery Roadmap for Lokoja-Ayingba, Okene-Itobe Roads

By Jabiru Hassan

The Federal Government has reviewed the delivery strategy for the Lokoja–Shintaku–Dekina–Anyigba road and the Okene–Ajaokuta–Itobe dual carriageway projects in Kogi State, warning contractors over delays and considering mutual termination of uncompleted sections.

Minister of Works, Senator David Umahi, disclosed this after a meeting with the contractors, CCECC Nigeria Ltd and TEC Engineering Company Nigeria Ltd, at the ministry’s headquarters in Abuja. He said the projects, awarded in 2022 and expected to be completed in 2024, had recorded poor performance despite substantial financial commitments.

Umahi expressed concern that CCECC, handling the 52.27km Okene–Ajaokuta–Itobe carriageway, had achieved only 1.97 percent completion despite receiving an advance payment of ₦2.5 billion. He directed the Director of Highways, North Central, to issue a warning letter to the firm, giving it 30 days to resume work and deliver results commensurate with the funds already received. He added that the unexecuted portion of the contract would be terminated to allow for re-procurement and enhanced execution.

Similarly, the minister noted that TEC Engineering Company Nigeria Ltd, handling the Lokoja–Shintaku–Dekina–Anyigba road with a spur to Ugbabo, had achieved just 1.04 percent progress after receiving ₦1 billion. He ordered the contractor to complete 3km of asphalt by December 2025, after which the project would be closed on a mutual basis, with payments reconciled according to milestones.

He stressed that while earlier funds would be assessed on the old rate, disbursements under the 2025 budget would be based on new rates. Umahi also directed the mutual termination of consultancy services on both projects, pending new procurement.

Present at the meeting were senior ministry officials, including Engr. I. D. Daikwo, Director of Highways, North Central; Engr. I. U. Usman, Deputy Director, Highways, North Central; Mr. Mohammed A. Ahmed, Director of Press and Public Relations; and Engr. Gana Musa Patiko, Federal Controller of Works, Kogi State.

Also in attendance were representatives of the contractors, Mr. Shaun, Marketing Manager of TEC Engineering, and Mr. Zhou, Senior Executive Director of CCECC Nigeria Ltd, as well as project consultants and the Kogi State Commissioner for Works, Hon. Muhammed A. Yusuf, who represented the state government.

Hot this week

Editors Urge Government To Create Safe, Enabling Environment For Journalists

· Ask security agents to find missing Vanguard journalist As...

EXCLUSIVE: Buhari orders probe of Isa Funtua, AMCON over keystone and Etisalat

Following the controversy generated by the leading opposition party,...

6 Signs your boyfriend thinks you are ugly -Take note of No. 2

They say there are three kinds of people; the...

2023: South-East, Middle Belt Forum Endorses Peter Obi

The South-East and Middle Belt Forum has endorsed the...

Commissioner Pledges Partnership with NDLEA to Curb Drug Abuse in Secondary Schools

By Muhammad Ibrahim, Sokoto The Sokoto State Commissioner for Basic...

Plateau Commissioner Usman Rates Mikang LGA Boss High on Performance

By Israel Adamu, Jos The Plateau State Commissioner for Local...

FEA, KEDCO and Bagaja Announce Commissioning of First 10MW Mini-Grids in Jigawa

By Jabiru Hassan Future Energies Africa (FEA), the core investor...

Gov. Ododo Enjoins Kogi People to Embrace Peace, Support His Administration

By Noah Ocheni, Lokoja Kogi State Governor, Ahmed Usman Ododo,...

Peter Obi: Obidients launch GO-MERD in A’Ibom

By Ogenyi Ogenyi Uyo Supporters of former Labour Party Presidential...

Israeli-Iranian Conflict: Implications for Africa

By Daudu Agaba Andrew Samuel The Israeli-Iranian conflict, often seen...

DSCHC Set to Expand Health Coverage to 10,000 Widows in the State

By Anne Azuka The Delta State Contributory Health Commission (DSCHC)...
spot_img

Related Articles

Popular Categories

spot_imgspot_img