JUST IN: Power Generation Rises to 4,173.20MW

Must read

The Nigerian electricity supply on Wednesday bounced to 4,173.20Mw from a total of 2,931Mw on Tuesday.

Findings showed that only 17 power plants were operational as at Tuesday as the National Control Centre, Oshogbo directed some of the Generation Companies (GenCos) to shut down from 12 midnight owing to high frequency.

Afam, Dandikowa and Ihovbor power plants stopped production completely generating 0Mw each at that time.

The Nigerian System Operator (SO) of the Transmission Company of Nigeria (TCN), which dropped the hint about the energy market, said the situation of energy generation, however, improved by 1,241.89Mw in the early hours of Wednesday.

It was an indication of a 42.37% increase in 24 hours when 20 power plants became operational.

Meanwhile, Afam IV & V (Gas) generated 181Mw with two units while Alaoji NIPP (Gas) produced 99.50Mw with one unit.

It said with three units, Azura-Edo IPP (Gas) produced 400Mw, Dandikowa (Hydro) generated 20.20Mw while Delta (Gas) 351Mw with eight units and Egbin (Steam) produced 282Mw with two units.

Copyright DAYBREAK NIGERIA.

All rights reserved. This material, and other digital content on this website, may not be reproduced, published, broadcast, rewritten or redistributed in whole or in part without prior express written permission from DAYBREAK NIGERIA.

More articles

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisement -

Latest article