Lagos-Ibadan rail: FG berates CCECC over slow pace of work

By Jennifer Y Omiloli

Transportation Minister Rotimi Amaechi expressed dissatisfaction with the China Civil Engineering Construction Corporation’s slow pace of work on the Lagos end of the Lagos-Ibadan railway standard gage.

He accused the contractor of refusing to mobilize his staff to site on the pretext that some sub-contractors were unable to supply the portion of their work.

Amaechi spoke during a $1.5 billion standard gauge rail project inspection in Ologun-Eru State area on Tuesday.

He said, “If I say I am impressed with the CCECC on the Lagos axis of this project, then I am lying. We are just not there in the Lagos area at all.

“We have resolved all the crises in Lagos; and I must commend the Lagos State Water Corporation people for resolving the water pipeline issue, which constituted a major hindrance to the project. After the resolution of this issue, the CCECC has refused to mobilise to site in Lagos.”

On excuses given by the contractor for the delay, Amaechi stated, “The CCECC gave reasons for the slow pace of work at the Lagos end. They claimed that the jobs given to some of the sub-contractors were not met. For instance, the person relocating the water pipes was expected to finish that by November 2; but now the person is asking for additional two months to complete that.

“The excuse given by the sub-contractor is that there are other issues that have to be solved before the water pipes can be relocated. For me, this excuse, although tenable, is not excusable. There is a need for them to speed up because the speed between part of Ogun and Ibadan is encouraging; but the speed from Apapa to Ebute-Meta and to some other parts of Lagos is discouraging. The solution to the water pipelines has been found, but relocation is what is delaying us now.”

On the December deadline given to the contractor to complete the project, the minister explained, “Don’t forget this is a three-year project that we are trying to complete within a year. As I speak, there are only three bridges remaining to be completed between Abeokuta and Ibadan. Between Ogun and Lagos, there are just few bridges remaining to be completed. We will keep putting pressure on them to make sure that the project is completed quickly.”

Hot this week

FRSC Launches Easter Patrol, Warns Against Speeding and Overloading

The Federal Road Safety Corps (FRSC) has commenced its...

Court Adjourns El-Rufai’s Bail Application Till Wednesday

…Returns to ICPC CustodyBy Achadu Gabriel, KadunaThe Federal High...

Kogi Governor Ododo Appoints Prof. M.S. Audu as Pro-Chancellor of PAAU Anyigba

The Governor of Kogi State, Ahmed Usman Ododo, has...

FCTA, Finland to Partner on Smart City, Waste Management Solutions

By Joyce Remi BabayejuThe Federal Capital Territory (FCT) Administration...

Pate Okays Nigeria-China Surveillance, Data, Preparedness, Disease Response Collaboration

By Joyce Remi BabayejuThe Coordinating Minister of Health and...

CS-SUNN Calls for Increased CNF to Tackle Child, Maternal Malnutrition in FCT

…As Stakeholders Warn of Poor Nutrition CultureBy Joyce Remi...

CWAI Commends Federal Fire Service CG Olumode for Strategic Direction, Institutional Reforms

The Citizens Watch Advocacy Initiative (CWAI) has praised the...

Leeds ‘Greedy for More’ as Wembley Semi-Final Beckons

Leeds United are daring to dream of FA Cup...

Lijnders Hints at Exit for Bernardo Silva from Manchester City

Pep Lijnders, assistant manager of Manchester City, has suggested...

Psychologists Say Calm People Use These 10 Phrases to Defuse Conflict

I used to shut down during arguments—not in a...

‘I Wasn’t Happy’ – Patience Ozokwor Opens Up on Being Forced Into Early Marriage

Veteran Nollywood actress, Patience Ozokwor, popularly known as Mama...

Related Articles

Popular Categories

spot_imgspot_img