Lagos-Ibadan rail: FG berates CCECC over slow pace of work

By Jennifer Y Omiloli

Transportation Minister Rotimi Amaechi expressed dissatisfaction with the China Civil Engineering Construction Corporation’s slow pace of work on the Lagos end of the Lagos-Ibadan railway standard gage.

He accused the contractor of refusing to mobilize his staff to site on the pretext that some sub-contractors were unable to supply the portion of their work.

Amaechi spoke during a $1.5 billion standard gauge rail project inspection in Ologun-Eru State area on Tuesday.

He said, “If I say I am impressed with the CCECC on the Lagos axis of this project, then I am lying. We are just not there in the Lagos area at all.

“We have resolved all the crises in Lagos; and I must commend the Lagos State Water Corporation people for resolving the water pipeline issue, which constituted a major hindrance to the project. After the resolution of this issue, the CCECC has refused to mobilise to site in Lagos.”

On excuses given by the contractor for the delay, Amaechi stated, “The CCECC gave reasons for the slow pace of work at the Lagos end. They claimed that the jobs given to some of the sub-contractors were not met. For instance, the person relocating the water pipes was expected to finish that by November 2; but now the person is asking for additional two months to complete that.

“The excuse given by the sub-contractor is that there are other issues that have to be solved before the water pipes can be relocated. For me, this excuse, although tenable, is not excusable. There is a need for them to speed up because the speed between part of Ogun and Ibadan is encouraging; but the speed from Apapa to Ebute-Meta and to some other parts of Lagos is discouraging. The solution to the water pipelines has been found, but relocation is what is delaying us now.”

On the December deadline given to the contractor to complete the project, the minister explained, “Don’t forget this is a three-year project that we are trying to complete within a year. As I speak, there are only three bridges remaining to be completed between Abeokuta and Ibadan. Between Ogun and Lagos, there are just few bridges remaining to be completed. We will keep putting pressure on them to make sure that the project is completed quickly.”

Hot this week

New Chelsea boss Rosenior faces FA Cup test

Liam Rosenior will take charge of Chelsea for the...

Tax law: States to gain N5tn VAT windfall as new sharing formula takes effect

Nigeria’s 36 states are projected to receive about N5.07tn...

Obio/Akpor: Wike Knocks Critics Over His Choice for Politics

By Joyce Remi-BabayejuThe FCT Minister, Barr. Nyesom Wike has...

EPL: Tottenham close in on £35m deal for Atletico midfielder Gallagher

Tottenham Hotspur are on the verge of signing Atletico...

Bandits Demand ₦500m Ransom for Abducted Kaduna Photojournalist, Kill One Captive

By Achadu Gabriel, KadunaArmed bandits have demanded a ransom...

Presidential Tax Committee Commends Kogi’s Progress in Tax Reform

From Noah Ocheni, LokojaThe Presidential Committee on Fiscal Policy...

PANDEF Reconciliation Committee Urges Calm, Forgiveness in Rivers State Crisis

By Wilfred FrancisAbuja, Nigeria - The PANDEF Reconciliation Committee,...

Group faults Gov Eno for APC flag at Uyo Town Centre

By Ogenyi Ogenyi, .UyoAn advocacy group in Akwa Ibom,...

U.S. Foreign Policy Shifts and Their Implications for Global Geopolitics

By Michael OnjewuIn an era where multilateralism is increasingly...

VAR errors rise to 13 in first half of EPL season

Video Assistant Referee (VAR) mistakes have increased during the...

Ondo governor marks 61st birthday with pardon for seven inmates

Ondo State Governor, Lucky Aiyedatiwa, has granted amnesty to...

Related Articles

Popular Categories

spot_imgspot_img