Lagos-Ibadan rail: FG berates CCECC over slow pace of work

By Jennifer Y Omiloli

Transportation Minister Rotimi Amaechi expressed dissatisfaction with the China Civil Engineering Construction Corporation’s slow pace of work on the Lagos end of the Lagos-Ibadan railway standard gage.

He accused the contractor of refusing to mobilize his staff to site on the pretext that some sub-contractors were unable to supply the portion of their work.

Amaechi spoke during a $1.5 billion standard gauge rail project inspection in Ologun-Eru State area on Tuesday.

He said, “If I say I am impressed with the CCECC on the Lagos axis of this project, then I am lying. We are just not there in the Lagos area at all.

“We have resolved all the crises in Lagos; and I must commend the Lagos State Water Corporation people for resolving the water pipeline issue, which constituted a major hindrance to the project. After the resolution of this issue, the CCECC has refused to mobilise to site in Lagos.”

On excuses given by the contractor for the delay, Amaechi stated, “The CCECC gave reasons for the slow pace of work at the Lagos end. They claimed that the jobs given to some of the sub-contractors were not met. For instance, the person relocating the water pipes was expected to finish that by November 2; but now the person is asking for additional two months to complete that.

“The excuse given by the sub-contractor is that there are other issues that have to be solved before the water pipes can be relocated. For me, this excuse, although tenable, is not excusable. There is a need for them to speed up because the speed between part of Ogun and Ibadan is encouraging; but the speed from Apapa to Ebute-Meta and to some other parts of Lagos is discouraging. The solution to the water pipelines has been found, but relocation is what is delaying us now.”

On the December deadline given to the contractor to complete the project, the minister explained, “Don’t forget this is a three-year project that we are trying to complete within a year. As I speak, there are only three bridges remaining to be completed between Abeokuta and Ibadan. Between Ogun and Lagos, there are just few bridges remaining to be completed. We will keep putting pressure on them to make sure that the project is completed quickly.”

Hot this week

JUST IN: Shettima visits Kwara community after deadly attack

Vice President Kashim Shettima on Saturday visited Woro village...

Bomb Scare Disrupts Activities at Bayelsa Secretariat, Police Arrest Suspect

Activities were disrupted at the Bayelsa State Civil Service...

Turkey: Osimhen Becomes Galatasaray’s Fourth-Highest Scoring Foreign Player [Top 5]

Galatasaray striker Victor Osimhen on Sunday etched his name...

Ganduje Lauds Mariya Mahmoud’s Grassroots-Driven Empowerment Initiative in Kano

By Joyce Remi-BabayejuFormer First Lady of Kano State, Prof....

Gunmen Kill One, Kidnap Woman in Kogi Border Community

By Noah Ocheni, LokojaOne person was killed and a...

Commodore Okokota Takes Over Command of NNS SOROH

Commodore Christian Okokota has officially assumed duty as the...

Uba Sani: I Will Make Kaduna an Industrial Hub

By Achadu Gabriel, KadunaGovernor has reiterated his administration’s commitment...

Diri Inaugurates APC Coordinators, Warns Against Division

Bayelsa State Governor, Senator , has inaugurated local government...

Alleged Passport Substitution: CSO Raises Alarm Over Irregular Practices in Some States

By Jabiru HassanA civil society organisation, Independent Hajj Reporters,...

Peace Envoy, Prof. Kwaja, Defects to APC in Plateau

By Israel Adamu, JosThe Special Envoy on Peace and...

Tems Becomes First African Female Artist with Seven Billboard Hot 100 Entries

Grammy-winning Nigerian singer Tems has made history as the...

Joe Adia Calls for Balanced Approach to NDDC Payments and Programmes

Joe Adia, Founder of the Contractors Association of the...

Related Articles

Popular Categories

spot_imgspot_img