Lagos-Ibadan rail: FG berates CCECC over slow pace of work

By Jennifer Y Omiloli

Transportation Minister Rotimi Amaechi expressed dissatisfaction with the China Civil Engineering Construction Corporation’s slow pace of work on the Lagos end of the Lagos-Ibadan railway standard gage.

He accused the contractor of refusing to mobilize his staff to site on the pretext that some sub-contractors were unable to supply the portion of their work.

Amaechi spoke during a $1.5 billion standard gauge rail project inspection in Ologun-Eru State area on Tuesday.

He said, “If I say I am impressed with the CCECC on the Lagos axis of this project, then I am lying. We are just not there in the Lagos area at all.

“We have resolved all the crises in Lagos; and I must commend the Lagos State Water Corporation people for resolving the water pipeline issue, which constituted a major hindrance to the project. After the resolution of this issue, the CCECC has refused to mobilise to site in Lagos.”

On excuses given by the contractor for the delay, Amaechi stated, “The CCECC gave reasons for the slow pace of work at the Lagos end. They claimed that the jobs given to some of the sub-contractors were not met. For instance, the person relocating the water pipes was expected to finish that by November 2; but now the person is asking for additional two months to complete that.

“The excuse given by the sub-contractor is that there are other issues that have to be solved before the water pipes can be relocated. For me, this excuse, although tenable, is not excusable. There is a need for them to speed up because the speed between part of Ogun and Ibadan is encouraging; but the speed from Apapa to Ebute-Meta and to some other parts of Lagos is discouraging. The solution to the water pipelines has been found, but relocation is what is delaying us now.”

On the December deadline given to the contractor to complete the project, the minister explained, “Don’t forget this is a three-year project that we are trying to complete within a year. As I speak, there are only three bridges remaining to be completed between Abeokuta and Ibadan. Between Ogun and Lagos, there are just few bridges remaining to be completed. We will keep putting pressure on them to make sure that the project is completed quickly.”

Hot this week

China’s ‘Two Sessions’ and the Opportunity for Africa

BY CHARLES ONUNAIJUA very significant event in China’s political...

BBNaija Star Ilebaye Undergoes Face And Nose Rejuvenation For Youthful Look

Reality TV personality Ilebaye Odiniya has revealed she recently...

Julius Berger demonstrates commitment to CSR as Academy graduates 36

Julius Berger Nigeria Plc has demonstrated its commitment to...

CACOL Condemns Growing Disregard for Legislative Oversight by Heads of Agencies

By Jabiru HassanThe Centre for Anti-Corruption and Open Leadership...

Senator Nora Daduut Congratulates Plateau Governor Caleb Mutfwang on 61st Birthday

By Golok Nanmwa, JosSenator Prof. Nora Ladi Daduut, Nigeria’s...

Julius Berger demonstrates commitment to CSR as Academy graduates 36

Julius Berger Nigeria Plc has demonstrated its commitment to...

US Spent $11bn on Iran War in First Six Days – Report

The United States spent more than $11.3 billion during...

Senator Nora Daduut Congratulates Plateau Governor Caleb Mutfwang on 61st Birthday

By Golok Nanmwa, JosSenator Prof. Nora Ladi Daduut, Nigeria’s...

Rainstorm Destroys Over 40 Houses, Churches in Kogi Community

From Noah Ocheni, LokojaResidents of Egbeda Egga community...

‘No Man Feels Complete When a Woman Is Feeding Him’ — Eucharia Anunobi

Veteran Nollywood actress Eucharia Anunobi has sparked debate on...

BBNaija Star Ilebaye Undergoes Face And Nose Rejuvenation For Youthful Look

Reality TV personality Ilebaye Odiniya has revealed she recently...

Court Allows PDP Factions Settle Convention Dispute Out of Court

The Court of Appeal sitting in Ibadan, Oyo State,...

Related Articles

Popular Categories

spot_imgspot_img