Lagos-Ibadan rail: FG berates CCECC over slow pace of work

By Jennifer Y Omiloli

Transportation Minister Rotimi Amaechi expressed dissatisfaction with the China Civil Engineering Construction Corporation’s slow pace of work on the Lagos end of the Lagos-Ibadan railway standard gage.

He accused the contractor of refusing to mobilize his staff to site on the pretext that some sub-contractors were unable to supply the portion of their work.

Amaechi spoke during a $1.5 billion standard gauge rail project inspection in Ologun-Eru State area on Tuesday.

He said, “If I say I am impressed with the CCECC on the Lagos axis of this project, then I am lying. We are just not there in the Lagos area at all.

“We have resolved all the crises in Lagos; and I must commend the Lagos State Water Corporation people for resolving the water pipeline issue, which constituted a major hindrance to the project. After the resolution of this issue, the CCECC has refused to mobilise to site in Lagos.”

On excuses given by the contractor for the delay, Amaechi stated, “The CCECC gave reasons for the slow pace of work at the Lagos end. They claimed that the jobs given to some of the sub-contractors were not met. For instance, the person relocating the water pipes was expected to finish that by November 2; but now the person is asking for additional two months to complete that.

“The excuse given by the sub-contractor is that there are other issues that have to be solved before the water pipes can be relocated. For me, this excuse, although tenable, is not excusable. There is a need for them to speed up because the speed between part of Ogun and Ibadan is encouraging; but the speed from Apapa to Ebute-Meta and to some other parts of Lagos is discouraging. The solution to the water pipelines has been found, but relocation is what is delaying us now.”

On the December deadline given to the contractor to complete the project, the minister explained, “Don’t forget this is a three-year project that we are trying to complete within a year. As I speak, there are only three bridges remaining to be completed between Abeokuta and Ibadan. Between Ogun and Lagos, there are just few bridges remaining to be completed. We will keep putting pressure on them to make sure that the project is completed quickly.”

Hot this week

2025: A Watershed Year for Consistent and Quality Legislation in Kano Assembly

By Kamaluddeen Sani ShawaiThe Kano State House of Assembly,...

Bayelsa Governor Diri Defends Party Switch, Urges Politicians to Defect on Conviction

By Amgbare Ekaunkumo, YenagoaBayelsa State Governor, Douye Diri, has...

Reps Intervene in Tug-of-War Over $1.2bn Gurara II Dam Project

By Oladosu Adebola OluwaseunThe House of Representatives has...

SPL: ‘You’re Not Close to Ronaldo’s Level’ — Al-Ittihad Legend Noor Blasts Benzema

Al-Ittihad legend Mohamed Noor has launched a scathing attack...

Police nab man in juju related armed robbery case in A’ibom

By Ogenyi Ogenyi,UyoThe Police in Akwa Ibom has arrested...

China, Nigeria Celebrate 2026 Chinese New Year, 55 Years of Diplomatic Ties

The Chinese Embassy in Nigeria on Saturday hosted a...

Nigeria–Türkiye Engagement Strengthens Security, Economic Cooperation

By Francis WilfredThe Federal Government has reaffirmed the strategic...

Olukoyede Cautions REDAN against Exposure to Financial Crimes

By Francis WilfredThe Executive Chairman of the Economic and...

Northern CAN Condoles with Victims of Kwara Massacre, Muslim Ummah

By Achadu Gabriel, KadunaThe Christian Association of Nigeria (CAN)...

NDLEA Seizes 7,746 Tonnes of Illicit Drugs, Arrests 339 Suspects in Kogi

By Noah Ocheni, LokojaThe National Drug Law Enforcement Agency...

Insecurity: Kaduna Community Protests Displacement of 18 Villages, Closure of 13 Schools

…As Bandits Resume ThreatsBy Achadu Gabriel, KadunaResidents of Kaso,...

Related Articles

Popular Categories

spot_imgspot_img