Lagos-Ibadan rail: FG berates CCECC over slow pace of work

By Jennifer Y Omiloli

Transportation Minister Rotimi Amaechi expressed dissatisfaction with the China Civil Engineering Construction Corporation’s slow pace of work on the Lagos end of the Lagos-Ibadan railway standard gage.

He accused the contractor of refusing to mobilize his staff to site on the pretext that some sub-contractors were unable to supply the portion of their work.

Amaechi spoke during a $1.5 billion standard gauge rail project inspection in Ologun-Eru State area on Tuesday.

He said, “If I say I am impressed with the CCECC on the Lagos axis of this project, then I am lying. We are just not there in the Lagos area at all.

“We have resolved all the crises in Lagos; and I must commend the Lagos State Water Corporation people for resolving the water pipeline issue, which constituted a major hindrance to the project. After the resolution of this issue, the CCECC has refused to mobilise to site in Lagos.”

On excuses given by the contractor for the delay, Amaechi stated, “The CCECC gave reasons for the slow pace of work at the Lagos end. They claimed that the jobs given to some of the sub-contractors were not met. For instance, the person relocating the water pipes was expected to finish that by November 2; but now the person is asking for additional two months to complete that.

“The excuse given by the sub-contractor is that there are other issues that have to be solved before the water pipes can be relocated. For me, this excuse, although tenable, is not excusable. There is a need for them to speed up because the speed between part of Ogun and Ibadan is encouraging; but the speed from Apapa to Ebute-Meta and to some other parts of Lagos is discouraging. The solution to the water pipelines has been found, but relocation is what is delaying us now.”

On the December deadline given to the contractor to complete the project, the minister explained, “Don’t forget this is a three-year project that we are trying to complete within a year. As I speak, there are only three bridges remaining to be completed between Abeokuta and Ibadan. Between Ogun and Lagos, there are just few bridges remaining to be completed. We will keep putting pressure on them to make sure that the project is completed quickly.”

Hot this week

Kano Commissioner Urges Deputy Governor to Resign After APC Defection

The Kano State Commissioner for Information and Internal Affairs,...

Indigenous Contractors Commend Minister of State Uzoka-Anite’s Swift Intervention On Oustanding Debts

A delegation of indigenous contractors across Nigeria has commended...

Accountability, Not Adulation, Should Guide Hajj Reporting

By Suleiman Bashar AliyuIn any healthy society, journalism serves...

Naira Strengthens to N1,385/$ as Equities Gain N232bn

The naira appreciated further at the official foreign exchange...

Army kills ISWAP commander, foils attacks in Borno

Troops of the Joint Task Force (North East), Operation...

Premier League Clubs Step Up Activity as January Transfer Window Nears Close

Premier League clubs intensified squad reshaping during the January...

March 31 Deadline: Oyedele Urges Nigerians to File Annual Tax Returns

Chairman of the Presidential Committee on Fiscal Policy and...

Crusade Dispute Puts CAN, PFN Under Spotlight

Allegations of interference and partiality have unsettled Nigeria’s major...

Accountability, Not Adulation, Should Guide Hajj Reporting

By Suleiman Bashar AliyuIn any healthy society, journalism serves...

Why Military Coups Are Re-Emerging Across Parts of Africa

A resurgence of military coups in parts of Africa...

North Central Development Commission Seeks Security Partnership in Nasarawa

The North Central Development Commission (NCDC) has begun consultations...

Kaduna Launches Sanitation Drive, Creates 5,000 Jobs for Youths and Women

Kaduna State Governor Uba Sani has launched a new...

Related Articles

Popular Categories

spot_imgspot_img