x

Julius Berger Begins Construction on Cotonou Road Bridges, Emphasizes Equal Opportunity and Workforce Diversity

Top engineering firm Julius Berger Nigeria Plc has launched the first phase of its construction projects in Cotonou, Republic of Benin. After completing preliminary work on the “Acces et Traverseé de Cotonou” (ATC 2) highway, the company has now commenced extensive rehabilitation efforts, including the reconstruction of access roads throughout the city.

During a recent visit to Section 1 of ATC 2, ongoing work on Roads 7, 9, and 10 was observed, with particular progress on Road 10, a key route for presidential travel to and from the airport. Despite high traffic, Julius Berger’s expertise is managing construction without disrupting flow.

Site Manager Vodounou Blaise shared insights into the complexities of the project, explaining that each construction phase starts with identifying and relocating underground network cables. “A lot of expertise and patience is required,” he noted, acknowledging weather challenges yet affirming steady progress.

Work includes drainage installation and slab placement on adjoining Road 9, along with upgrading interlocking stones in preparation for asphalt paving. Blaise added that collaboration with a government engineer has fostered community support, helping maintain a smooth operation.

On Road 7, demolition of old pavements and concrete walls has begun. At Julius Berger’s workshop in Cotonou, workers were completing installations, while the nearby asphalt plant at Calavi is nearing operational status. Workshop Supervisor Mr. Noal Lacey noted, “The mixer will be done by Thursday; then we’ll move to screens, filters, and bins. Soon, this 200-tonne-per-hour asphalt plant will be operational.”

Promoting Equal Opportunity and Diversity

Julius Berger upholds its commitment to equal opportunity and ethnic diversity in its workforce. Head of Projects Christoph Fierrens emphasized the company’s inclusive ethos, supporting a diverse team from Benin, Burkina Faso, Côte d’Ivoire, Ghana, Togo, Nigeria, and Benin. “We promote teamwork and collaboration, vital for meeting project deadlines,” he stated.

Highlighting the scope of work, Fierrens said Roads 9 and 10 and key aspects of the asphalt plant are set for completion this year. “We’re demolishing old pavements, retaining walls, and various concrete structures while surveying network areas to ensure timely project delivery,” he concluded.

Hot this week

COCSON Defends Umahi, Urges Due Process in Sowore Confrontation

The Coalition of Civil Society Organisations in Nigeria (COCSON)...

Nigeria’s First Lady, Oluremi Tinubu, A Blessing To Nigerians – Oborevwori

By Anne Azuka Delta State Governor, Rt. Hon. Sheriff Oborevwori...

Tinubu’s Commitment to State Police, a Generational Legacy — Kogi Govt

From Noah Ocheni, LokojaThe Government has described President ’s...

Mercy Johnson-Okojie and Daughter Purity Lead Girls Tag: Advancing Women’s Empowerment Through Period Care

Across Nigeria, conversations about gender equality and women’s empowerment...

Policie nab child abductor in A’ibom

By Ogenyi Ogenyi,UyoThe Police in Akwa Ibom has arrested...

Bayelsa NUJ Commends Diri’s Appointments, Seeks Urgent Action on Power Supply

The Nigeria Union of Journalists (NUJ), Bayelsa State Council,...

CBN RATE CUT OF 26.5: VOICES, UPSETS AND PROSPECTS

Adefolarin A. OlamilekanArguably, the latest 26.5% Central Bank of...

COCSON Defends Umahi, Urges Due Process in Sowore Confrontation

The Coalition of Civil Society Organisations in Nigeria (COCSON)...

Senate Rejects Opposition Call to Amend Electoral Act 2026

The Senate has dismissed calls by opposition leaders for...

Related Articles

Popular Categories

spot_imgspot_img