Senate committee calls for adequate funding of $530m Abuja, Keffi, Makurdi road

The House committee on works led by its Chairman Hon. Engr. Abubakar Kabir has deried the poor funding of the Abuja, Keffi, Makurdi dualisation project, while charging the contractor China Harbour on quality.

Hon Abubakar stated this while leading his committee on oversight over the road project.

The 220km Abuja, Keffi, Makurdi dualization is financed with Chinese counterpart funding of 85%( amounting to 460,822,440.20) while the Nigerian government is contributing 15% (amounting to 81,321,607.09) bringing the total contract sum to over $530m.

The project is divided into two components which are the addition of two lanes on the existing dual carriage from Kugbo in Abuja to the border of Nassarawa state, which is about 5.2 kilometers and the addition of another carriageway to the existing keffi- Akwanga-Lafia-Makurdi road which is about 221.8km long.

The committee chairman decried the inadequate release of counterpart funds for the project noting that it wad a major problem for the timely completion of the road.

“We asked them about their challenges and concerns, one of which was funding for the project and budgetary allocation. But last year, we provided a lot of funding for this project and the new budget is coming in the next few weeks”.

Speaking in the same vein the project manager, Mr. Lixiang Qiang, said the contractor was doing its best to ensure timely completion of the road and employed the FG government to release its counterpart funding for the project.

“this project has been ongoing on for 3years, we have a plan in place and we want to finish this project next year. Currently we are preparing for the funding to ensure processing and successful completion of the work.

“We are processing the budget and compensation issues, we have completed around 72% but our payment is 60%. The project is very long, that is why it is very important for us to get a budget each year so that the program can move accordingly”.

Addressing the ‘failed portions’ of the road, he expressed sadness and promised the problems would be rectified “I’m sad to see these sections, the failures should not be happening because we followed the procedures and specifications. We need to go back and analyze what happened with the road, in my opinion the water level of the area is too high”.

He assured that all concerns would be rectified before the road is handed over to the FG.

On completion the road is expected to last for 15 years before requiring maintenance.

Hot this week

Kaduna Journalists Trained on Digital Tools to Strengthen Peace Reporting

By Achadu Gabriel, KadunaSixty journalists and media practitioners in...

Over 40 Nigerians Graduate from Chinese Language Program in Abuja

More than 40 Nigerians have completed the first phase...

Plateau Doctors Issue 7-Day Ultimatum Over Pay, Warn of Possible Strike

By Israel Adamu, JosResident doctors and other medical practitioners...

Zawan Group Calls for Fair Political Zoning in Jos South Ahead of 2027 Elections

By Israel Adamu, JosA socio-political group, Zawan Vanguard, has...

Abuja Residents Applaud Tinubu, Wike Over Satellite Town Roads

By Joyce Remi-BabayejuResidents of satellite communities in Abuja, particularly...

Price of aviation fuel crippling our operations- Ibom Air

By Ogenyi Ogenyi,UyoThe management of Ibom Air has called...

Nigerian Stars Shine Across Europe: Osimhen, Olayinka and Ibrahim Lead the Charge

Nigerian footballers delivered standout performances across Europe over the...

Ibom Air donates 50,000 doses of anti-malaria drugs to A’Ibom

By Ogenyi Ogenyi, UyoThe management of Ibom Airlines Limited...

Methodist Church Raises Concerns Over Insecurity, Hardship, Governance Challenges

By Achadu Gabriel, KadunaThe Methodist Church Nigeria, Diocese of...

Kogi Deepens China Partnership to Advance Agro-Industrial Programme

By Noah Ocheni, LokojaThe Kogi State Government says it...

Maktown Flyers Secure First BAL Win as Igoche Mark Urges Focus Ahead of Next Games

Nigerian basketball promoter Igoche Mark has congratulated Maktown Flyers...

FG Flags Off Construction Of Ecumenical Airport Chapel And Pilgrims Centre

By Francis WilfredThe Federal Government has performed the...

Related Articles

Popular Categories

spot_imgspot_img