Senate committee calls for adequate funding of $530m Abuja, Keffi, Makurdi road

The House committee on works led by its Chairman Hon. Engr. Abubakar Kabir has deried the poor funding of the Abuja, Keffi, Makurdi dualisation project, while charging the contractor China Harbour on quality.

Hon Abubakar stated this while leading his committee on oversight over the road project.

The 220km Abuja, Keffi, Makurdi dualization is financed with Chinese counterpart funding of 85%( amounting to 460,822,440.20) while the Nigerian government is contributing 15% (amounting to 81,321,607.09) bringing the total contract sum to over $530m.

The project is divided into two components which are the addition of two lanes on the existing dual carriage from Kugbo in Abuja to the border of Nassarawa state, which is about 5.2 kilometers and the addition of another carriageway to the existing keffi- Akwanga-Lafia-Makurdi road which is about 221.8km long.

The committee chairman decried the inadequate release of counterpart funds for the project noting that it wad a major problem for the timely completion of the road.

“We asked them about their challenges and concerns, one of which was funding for the project and budgetary allocation. But last year, we provided a lot of funding for this project and the new budget is coming in the next few weeks”.

Speaking in the same vein the project manager, Mr. Lixiang Qiang, said the contractor was doing its best to ensure timely completion of the road and employed the FG government to release its counterpart funding for the project.

“this project has been ongoing on for 3years, we have a plan in place and we want to finish this project next year. Currently we are preparing for the funding to ensure processing and successful completion of the work.

“We are processing the budget and compensation issues, we have completed around 72% but our payment is 60%. The project is very long, that is why it is very important for us to get a budget each year so that the program can move accordingly”.

Addressing the ‘failed portions’ of the road, he expressed sadness and promised the problems would be rectified “I’m sad to see these sections, the failures should not be happening because we followed the procedures and specifications. We need to go back and analyze what happened with the road, in my opinion the water level of the area is too high”.

He assured that all concerns would be rectified before the road is handed over to the FG.

On completion the road is expected to last for 15 years before requiring maintenance.

Hot this week

Former Presidential Candidate Urges Tinubu, Atiku, Obi to Engage in Policy Debate

A former presidential candidate of the defunct African Renaissance...

Oborevwori Condemns Police Killing, Vows Justice For Slain Delta Youth

By Anne Azuka Delta State Governor, Rt. Hon. Sheriff Oborevwori,...

Idris: As Nigeria’s Chief Image Maker Turns 60

By Simon ReefUnlike in the past, when the Federal...

Idris: As Nigeria’s Chief Image Maker Turns 60

By Simon ReefUnlike in the past, when the Federal...

Diri Approves 108 Houses For Bayelsa Civil Servants

Governor Douye Diri of Bayelsa State has approved the...

Workers’ Day: Ododo Reaffirms Commitment to Workers’ Welfare as Labour Submits Fresh Demands

From Noah Ocheni, LokojaGovernor has reaffirmed his administration’s commitment...

Otuan Backs Dr. Tokpo for Bayelsa Assembly Seat

Leaders of the Otuan Federated Communities in Southern Ijaw...

Kaduna Gov Praises Tinubu for Approving Over N1trn Contracts to Transform State

By Achadu Gabriel, KadunaKaduna State Governor, , has commended...

Rights Group to sue Police over alleged land grabbing in Akwa Ibom

By Ogenyi Ogenyi, UyoHuman Rights lawyer and Chairman, Akwa...

Falgore Describes Workers as the Engine Room for Positive Change

By Jabiru HassanThe Speaker of the Kano State House...

IHR Sets Up 2026 Hajj Media Monitoring Team

By Jabiru HassanIndependent Hajj Reporters (IHR), a faith-based civil...

Related Articles

Popular Categories

spot_imgspot_img